Kingston, Ont., — the rail overpass on John Counter Boulevard next to the Via station.Thursday was a concrete pour day. In fact, it was the third of five such days.
The focus at this point is the deck of the bridge, says Rob Lambert, the city’s construction project manager.“This pour right now, the centre span is just under 180 cubic metres of concrete that they’re doing today.
The bridge itself has over 800 cubic metres for the deck and then the re-bar in the deck itself, which is all the steel that you can see today, it’s just over shy of two tons.”While the provincial response to the COVID-19 pandemic resulted in business and service shut-downs, Lambert says it hasn’t taken much of a toll on the $40-million overpass project.